Oct 22, 2021 | Uncategorized
Update for Week of October 25: This past week, the Contractor finished the construction of the duct bank on the North and Southside of Frost Street. They have begun similar construction on the western side of Main Street from the north side of Frost in front of Johnny...
Oct 8, 2021 | Uncategorized
Visiting today’s Marshall Farmers Market & 2nd Friday event? Many of our Main Street businesses offer parking on-site! Additional parking can be found just past the Market along West Main Street and in the Marshall United Methodist Church parking lot. Please...
Sep 30, 2021 | Uncategorized
Additional 15-minute parking spaces have been opened up along West Main Street! The parking areas are in front of: Aaron Mormann – State Farm Insurance Agent 8354 West Main Street The Crafter’s Consignment Store (Opening 10/16) Basement Cuts Blue-a-salon...
Aug 20, 2021 | Uncategorized
Due to weather, tonight’s Marshall Farmers Market has been moved indoors to the Marshall Ruritan Club located at 8400 Salem Avenue. The event will run from 4 pm – 7 pm and will feature local agriculture, craft, and artisan producers from our own...
Jun 30, 2021 | Uncategorized
Marshall’s next Farmers Market & 2nd Friday event will take place on Friday, July 9th starting at 4 pm! The H&H Auto Garage parking lot will play host to local agricultural, craft, and artisan producers while our Main Street businesses stay open a little bit...
Jun 11, 2021 | Uncategorized
With consistent rain occurring throughout the day that will make for very unpleasant conditions this afternoon the Marshall Farmers Market has been canceled. We do however encourage you to still visit the Main Street businesses that will be open for this month’s...
May 25, 2021 | Uncategorized
Marshall’s next Farmer’s Market & 2nd Friday event will take place on Friday, June 11th starting at 4 pm! The H&H Auto Garage parking lot will play host to local agricultural, craft, and artisan producers while our Main Street businesses stay open a...
Mar 25, 2021 | Uncategorized
This week, Shirley Contracting will be completing pre-construction activities and mobilization for the Marshall Main Street Improvements Project. Below is an overview of work areas and an estimated timeline in order of work. Please note, the weather may impact this...
Feb 20, 2021 | Uncategorized
Over the next month, Shirley Contracting, will begin construction on the Marshall Main Street Improvements Project. They are currently completing pre-construction activities and mobilization. During this time, Shirley or their sub-contractors will be on-site to...
Dec 24, 2020 | Uncategorized
From our little corner of the world wishing you and yours Happy holidays and a rich and prosperous New year!