This week, Shirley Contracting will be completing pre-construction activities and mobilization for the Marshall Main Street Improvements Project. Below is an overview of work areas and an estimated timeline in order of work. Please note, the weather may impact this schedule and will be updated accordingly.

Main Street (westbound): 2-3 days, 3/25-3/26 to 3/26-3/29
Rectortown Road: 1-2 days, 3/29-3/30 to 3/30-3/31